MKH Annual Report 2020
210 FINANCIAL STATEMENTS ANNUAL REPORT 2020 36. CONTINGENT LIABILITIES (CONT’D) The DGT may appeal to Supreme Court, nevertheless, the directors of PTMKH are of the opinion that PTMKH has a valid defense against DGT’s assessment for both years of assessment 2012 and 2013. Furthermore, on 27 July 2020 PTMKH has received a tax refund from the tax authorities amounting to IDR3,875 million, equivalent to RM1.1 million, which is deemed as an acceptance of the Court decision. Accordingly, PTMKH has not made any adjustments in respect of the tax assessments in the financial statements. (b) On 11 January 2019, the recipient of KTM Komuter Station, Perbadanan Aset Keretapi (“PAK”) has issued a certificate of non-completion (“CNC”) to Srijang Kemajuan Sdn. Bhd. (“SKSB”), a 99.99% owned subsidiary of the Company, and stating that SKSB has failed to complete the construction of KTM Komuter Station (“Construction Works”) by 10 December 2016 and therefore PAK is entitled to impose liquidated ascertained damages (“LAD”) pursuant to the Development cum Lease Agreement (“DCLA”) dated 12 October 2012 entered into between PAK and SKSB. The LAD will be calculated daily at a rate of RM4,438.36 from the revised completion date on 10 December 2016 (extension of time number 1) until the completion of the Construction Works. On 28 February 2019, SKSB has written to dispute the validity of the CNC on the grounds that SKSB had on 10 January 2017 submitted extension of time (“EOT”) number 2 of which PAK has yet to assess SKSB’s application for EOT number 2 and on the same day, SKSB submitted EOT number 3 in view of the delay by relevant authorities in approving the change of building design and use of building materials. On 19 August 2019, PAK granted SKSB’s EOT number 2, for a period of up to 8 January 2017 (“EOT 2”). On 13 January 2020, SKSB has written to appeal for the EOT 2 to be extended to 30 December 2017 instead of 8 January 2017. On 15 June 2020, SKSB submitted EOT number 4, for period from 11 April 2020 to 1 July 2020 together with the above mentioned EOT 2 (period from 11 December 2016 to 30 December 2017) and EOT number 3 (“EOT 3”) (period from 31 December 2017 to 10 April 2020). Based on legal opinion obtained, the directors of SKSB are of the opinion that SKSB’s LAD could not be estimated until and unless PAK has completed the assessment of EOT 3 as the date by which SKSB is required to complete the Construction Works remains uncertain. In view of the uncertainty, there is no revised completion date from which the LAD could be computed and PAK’s right to impose LAD pursuant to DCLA cannot be triggered. Accordingly, SKSB has not made any provision in the financial statements and only disclosed as contingent liabilities.
Made with FlippingBook
RkJQdWJsaXNoZXIy NDgzMzc=